LOD in BIM: Levels 100 to 500 Explained
LOD in BIM stands for Level of Development: a scale from LOD 100 to LOD 500 that states how far each element in a building model has been developed, and therefore how much a project team can rely on it. The scale is published by BIMForum in its Level of Development (LOD) Specification, built on definitions from AIA Contract Documents. This guide gives the short definition of every level, explains how LOD differs from level of detail, LOI and LOA, and says which levels are normal when a model is made from a laser scan of an existing building.
What is LOD in BIM
LOD describes a single model element, not the whole model. A wall, a duct and a pump can sit at different levels in the same file. The BIMForum specification calls itself “a reference tool intended to improve the quality of communication among users of Building Information Models (BIMs) about the characteristics of elements in models.” It does not tell a project which level to use: “it does not prescribe the necessary levels of development for different steps in the construction process. That determination is left to each project team.”
Two properties of the scale matter in practice. The levels are cumulative: requirements for each LOD (except LOD 500) “include the requirements for all lower LODs.” And the specification is revised in new editions; the one cited here is the 2023 edition, in its own words a “10th Anniversary Edition,” and its Part I holds the level definitions.
Where the LOD scale comes from
The AIA published the first LOD definitions in 2008, in document E202-2008, the Building Information Modeling Protocol. It updated them for G202-2013 and again for E201-2022, the BIM Exhibit for Sharing Models with Project Participants. BIMForum started its specification in 2011. A working group interpreted the AIA definitions system by system (walls, structure, mechanical and so on) and added drawings and tables. It also added LOD 350, which the AIA definitions did not have at first. The 2022 AIA digital practice documents now include LOD 350.
What is the difference between level of detail and level of development
Many people say “level of detail” for LOD, and search results use both. BIMForum separates them: “Level of Detail is essentially how much detail is included in the model element. Level of Development is the degree to which the element’s geometry has been thought through” and “the degree to which project team members may rely on the information when using the model.” The specification uses Level of Development and notes that “some countries refer to the Level of Development concept defined within this specification as the Level of Detail and use different numbering systems.” In US contracts and BIMForum documents, LOD means Level of Development.
LOD 100, 200, 300, 350, 400 and 500
The wording below is the BIMForum Part I fundamental definition for each level, with the BIMForum interpretation condensed.
LOD 100. The element “may be graphically represented in the Model with a symbol or other generic representation.” Symbols show that a component exists but not “its shape, size, or precise location,” and space reservation volumes also sit here. Information derived from LOD 100 elements “must be considered approximate.”
LOD 200. The element is “generically and graphically represented within the Model with approximate quantity, size, shape, location, and orientation.” These are generic placeholders, but they are recognizable as what they represent (a pump, a beam, a light fixture).
LOD 300. The element, as designed, is represented “such that its quantity, size, shape, location, and orientation can be measured.” BIMForum reads this as sufficiently developed to “fully convey the design intent.” Our guide What Is BIM LOD 300? covers this level in depth.
LOD 350. Adds the element’s “interfaces with adjacent or dependent Model Elements.” It exists to support “construction-level coordination,” and BIMForum notes it “usually requires craft knowledge.”
LOD 400. “Detail sufficient for fabrication, assembly, and installation.” BIMForum describes it as “developed to the level of shop drawings” and notes that most models contain few LOD 400 elements.
LOD 500. “A graphic representation of an existing or as-constructed condition developed through a combination of observation, field verification, or interpolation. The level of accuracy shall be noted or attached to the Model Element.”
| Level | What the element is | Typical use |
|---|---|---|
| LOD 100 | Symbol, generic representation or space reservation volume | Early massing, area and cost per square foot estimates |
| LOD 200 | Generic, recognizable placeholder with approximate size, shape, location | Schematic design, planning, approximate quantities |
| LOD 300 | As designed, can be measured for quantity, size, shape, location, orientation | Design development, construction documents, design intent |
| LOD 350 | LOD 300 plus interfaces with adjacent or dependent elements | Construction-level coordination, clash detection |
| LOD 400 | Detail for fabrication, assembly and installation | Shop drawings, fabrication |
| LOD 500 | Existing or as-constructed condition, observed or field verified, accuracy stated | Existing conditions, as-built documentation |
The “typical use” column is a common reading and not part of the specification. BIMForum states the three uses it had in mind when writing the definitions: quantity take-off, 3D coordination, and 3D control and planning.
Is LOD 500 more detailed than LOD 400
No. BIMForum says directly: “LOD 500 does not indicate a higher level than LOD 400, rather it indicates that the element’s geometry is determined through observation of an existing item rather than design of a future item.” The 2022 definition update made this explicit: LOD 500 applies to existing elements, while LODs 100 to 400 address “as-designed” elements. BIMForum has not written element-by-element interpretations for LOD 500, because the AIA’s definition concerned only field verification.
How accurate is an existing conditions model
LOD says how developed an element is, not how closely it matches the building. For existing conditions BIMForum points elsewhere: the LOD 500 definition “requires that the model element’s accuracy be specified,” and BIMForum “recommends USIBD’s Level of Accuracy (LOA) Specification for this purpose.” USIBD’s LOA is a separate specification, currently at version 3.1, for documenting and verifying the accuracy of building documentation deliverables. A model scoped as LOD 300 can carry an accuracy statement of its own, for example LOA30, and the two should be written into the scope separately.
LOD vs LOI vs LOA
| Term | Measures | Where it comes from |
|---|---|---|
| LOD, Level of Development | How far an element’s geometry is developed and how far it can be relied on | BIMForum, based on AIA definitions |
| LOI, Level of Information | How much non-geometric data (materials, manufacturer, ratings) is attached to elements | Used alongside LOD in BIM execution plans |
| LOA, Level of Accuracy | How closely measurements match the real building | USIBD |
BIMForum Part I addresses geometry only: “any number of non-geometric attributes can be attached to a model element of any LOD,” so non-geometric information is not covered there. A scope that says only “LOD 300” leaves the data and the accuracy undefined. LOD is also not the same thing as the UK BIM maturity levels 0 to 3, which describe how a project shares information, not how developed an element is.
Which LOD is used for scan-to-BIM
For a model built from a laser scan of an existing building, the usual choices are these:
- LOD 200 for massing, space planning, feasibility and area studies, where approximate size and location are enough.
- LOD 300 for design work: renovation drawings, permit sets, and anything an architect or engineer will design against. Elements are modeled at measured size and location.
- LOD 350 where mechanical, electrical and plumbing coordination needs connections, supports and interfaces between systems. See MEP and facility scanning.
Because a scan records the building as it stands, the result is an existing-condition model, and its accuracy is a property of the scan and the modeling, so name the LOA beside the LOD. The comparison of the two most requested levels is in LOD 200 vs LOD 300 for Scan-to-BIM, ceilings and plenums are covered in Scan-to-BIM for Ceilings and Plenums, and what the LOD changes in price is in the cost guide. We deliver scan-to-BIM Revit models from a registered point cloud at the LOD named in the scope.
FAQ
What is LOD in BIM?
LOD is Level of Development, a scale from 100 to 500 published by BIMForum that states how far a model element has been developed and how much a team can rely on it. It applies to each element, not to the model as a whole.
What is the difference between level of detail and level of development in BIM?
Level of detail is how much detail an element contains. BIMForum’s Level of Development is the degree to which the element’s geometry has been thought through and can be relied on. In US practice the two letters LOD mean Level of Development.
What do LOD 100, 200, 300, 400 and 500 mean?
LOD 100 is a symbol or space reservation, LOD 200 a generic recognizable element with approximate size and location, LOD 300 an as-designed element that can be measured, LOD 400 detail for fabrication and installation, and LOD 500 an existing or as-constructed condition with stated accuracy. BIMForum also defines LOD 350, which adds interfaces with adjacent elements.
Is LOD 500 higher than LOD 400?
No. LOD 500 means the geometry comes from observation of an existing item instead of design of a future one, and its accuracy must be specified.
Is LOD the same as BIM levels 0 to 3?
No. The UK BIM levels describe how a project shares information. LOD describes how developed each model element is.
Which LOD do I need for an existing building?
Most renovation design work uses LOD 300, and planning studies use LOD 200. Add LOD 350 where MEP coordination needs connections. State the LOA for accuracy in the same scope.
Sources
- BIMForum, Level of Development (LOD) Specification Part I, 2023 edition: all LOD definitions and quotes, the AIA lineage (E202-2008, G202-2013, E201-2022), level of detail vs development, LOD 500 and the LOA recommendation.
- USIBD, Level of Accuracy: LOA as a standard for documenting and verifying accuracy, current version 3.1.